GEN II ECOTEC LGE - Concrete Floor Replacement - Spring Hill, Tennessee

Spring Hill Manufacturing

Services: Renovation

Contract: General Contractor

Square Footage: 500,000

Owner: General Motors
100 Saturn Parkway
Springhill, TN 37174

Architect: SSOE
214 Centerview Drive, Suite 300
Brentwood, TN 37027

LaSalle was contracted by General Motors to demolish and remove 500,000 square feet of concrete floor ranging in thickness from 8” to over 5’. The scope also included the removal of existing machine foundations, engine line flumes and pits as well as the preparation and placement of a new 12” floor slab to accommodate a new mid-size engine line. The project required 19,000 cubic yards of concrete with each pour averaging 1,100 cubic yards or 30,000 square feet. All work was completed in 120 days.